| The Dismantaling of the Steel Works |
|---|
On the 31st July 2002, Ebbw Vale Works closed its gates as an operational site for the final time, this is the next chapter in the remarkable story of the Works that had commenced an iron & steel making operation in 1790. The demolition of the Works is the first phase in regeneration of the Ebbw valley as it makes a step change from its heritage as a world leader in the manufacture of iron and steel, to its future development as defined by the Master plan. |
| Site Decommissioning |
Following the closure announcement in February 2001, sixteen Decommissioning Managers/Engineers (Bottom of this page) were selected for their expertise in their specific plant areas, they would be responsible for all aspects of planning and de-commissioning plant within their area. The planning process included the allocation of resources and manpower to achieve de-commissioning of the site within a three-month window. Each area was broken down from the plant register of equipment to its particular plant identification number to ensure all items of plant and equipment would be included in the planning programme and subsequently decommissioned. It was recognised from the early planning stage that an item of kit de-commissioned post closure may not be demolished for up to three years following closure. Therefore, it was essential from a health and safety perspective to ensure all kit was de-commissioned and recorded as such in the de-commissioning log for the specific plant area, e.g. all equipment with the potential to store motive power, such as a belt wrapper, would be decommissioned and isolated in the lowered position. Pre-closure planning also included the reduction of chemical and oil stocks to minimise the waste of raw materials. First phase de-commissioning of the production units by line crews, i.e. dumping of line solutions to the Effluent Plant, as lines shut down, prior to plant closure. Targets were set for de-commissioning of chemical, oil, cooling and gas systems etc. Also to ensure safety standards were maintained during the de-commissioning process, the Risk Assessment and Job Method Statements identified all safety aspects associated with each individual plant item to be de-commissioned. For example: isolation procedures for electrical and stored energy systems, personal protective equipment requirements, standard working practices, and COSHH (Control of Substances Hazardous to Health) Assessments. Electrical, steam and compressed air systems were all de-commissioned by switching off at source by specific specialist engineers within the de-commissioning team, e.g. electrical supply was switched off at the central sub-sfation. Similarly, a specialist contractor purged the natural gas system with nitrogen, to prevent the risk of explosion or fire during the demolition phase. |
| Asset Transfer Programme |
In parallel with the de-commissioning process, the De-commissioning Managers were also responsible for managing the removal and transfer of assets to other Corus sites. The main objective of the asset disposal programme was to manage the transfer of redundant assets within the CPP/Corus businesses, to maximise the benefit of the asset to Corus and improve performance and productivity at other sites. Three options were evaluated in the process of maximising the benefit to Corus, firstly the transfer of assets (plant, equipment and spares) within the Corus businesses; secondly, external sale of the asset through an appointed agent. Finally, if the first two options were not achievable, the equipment and spares would be scrapped as part of the demolition process. Prior to closure both 4 ETL and the D.R. Mill were transferred to Trostre and Ijmuiden respectively, while post closure the Galvanising Line and Lurgi acid recovery plant were transferred to India. |
| Demolition Contracts - Assessment |
| To evaluate demolition experiences within the Company and establish best practice, Closure Managers at Ravenscraig and Panteg were visited. These visits enabled the Ebbw Vale Closure Team to gain valuable experience in understanding the human resources, health & safety and environmental aspects of planning the closure and demolition of a Steelworks. To fulfil its objectives to demolish and make the site safe and environmentally secure, CPP commenced demolition contractor assessment in October 2001, initially selecting 6 demolition contractors from the National Federation of Demolition Contractors that had proven experience of demolishing large sites, in particular steel sites such as Ravenscraig. To comply with CPP requirements to tender for the demolition works, each contractor had to agree to be spot audited, i.e. 15 minutes notice of arrival on a working demolition site. Audits were conducted to a specific questionnaire covering all safety, welfare and environmental aspects of demolition. Eventually, through an exhaustive tendering, audit and commercial meeting programme, a single demolition contractor was selected to demolish the Ebbw Vale site. David Morton (Larbert) Ltd. of Falkirk, Scotland, was awarded the contract. |
| Site Security |
The site covers approximately 189 acres and is secured by 5.5 km of 2111 high palisade fencing; to maintain security standards CPP security staff' were retained throughout the demolition programme. The post closure security envelope implemented on site closure included erecting an additional 1 kilometre of fence to isolate the southern end of the site, further fencing was erected at potentially intrusive points and visual black-spots. |
| Health & Safety in Demolition |
| Health & Safety demolition is controlled under the Construction, Design & Management Regulations (CDM) that places Health & Safety duties on all parties involved in the demolition project. Under the CDM Regulations, Health & Safety must be taken into account and then co-ordinated and managed effectively throughout all stages of the demolition project; from conception, design and planning through to the execution of the demolition works on site. It places Health & Safety responsibilities on the client, Planning Supervisor and Principal Contractor to produce from the tendering stage of the project a Health & Safety plan to be evolved throughout the demolition project, and recorded by a competent person(s) in the form of a Health & Safety file. This was developed at Ebbw Vale from the tendering stage through to the demolition by producing appropriate Risk Assessments for the demolition works. Risk Assessments and Job Method Statements were then prepared for the daily demolition sequence. This was reviewed at the daily Safety Meeting with the Demolition and Cleaning Contractors, where all aspects of safety were monitored and controlled. Monthly meetings were held which focused on pre-planning of the Health & Safety programme for the demolition works. A safety and environmental audit programme, undertaken in partnership with the contractors, of demolition activities supported this on site, to ensure health and safety/environmental standards were adhered to and maintained. To ensure all hazards were identified for the initial risk assessment, a comprehensive site register was compiled to include asbestos, chemicals, oils, buildings and basement structures, site drainage, land quality, COSHH (Control of Substances Hazardous to Health) assessments, site services electricity, gas, water etc., historical mine workings and sub-structures, rail und roadways, production line processes, machinery and equipment. The Kite register was continually up-dated and managed throughout the demolition programme to reflect the current site status. Prior to closure all aspects of the site Health & Safety controls were reviewed and amended accordingly from an operational to a closed site. This included new safety inductions and procedures for all CPP personnel, .contractor employees and visitors, to ensure all persons were aware of the hazards associated with the continually changing demolition works. |
| Evironmental Management - ISO 14001 |
| Ebbw Vale Works achieved certification to the ISO 14001 Environmental Management Standard in October 1999, as an operational site. CPP recognised that during the demolition programme the work may impact on (he environment in a number of ways, and were committed to minimising the effects of such activity wherever practicably possible. Therefore, to ensure the site was de-commissioned and demolished to the highest Environmental standards, a decision was made to retain ISO 1400 I .ert i fication throughout the de-commissioning and demolition process, Lloyds Q.A, on the revised Environmental Management System conducted tI successful re-certification audit in February 2003. The certificate issued for Project Management of Closure and Demolition of a Steel Plant. |
| Releases to the Environment |
| Environmental Authorisations held for the site combustion processes, acid regeneration Plant and Galvanising Line, were revoked to comply with environment Agency procedures. Similarly, licences held for radioactive Sources, legioella and COMAH (Control Of Major Accidents & Hazards) were revoked by the competent authority. Effluent Plant discharge consent licences were retained throughout the demolition programme for both controlled waters and foul sewer, and revoked on completion of the demolition works. |
| Site Investigation - Land Quality |
To fulfil its environmental obligations CPP appointed an independent Environmental Consultant to undertake a land quality investigation. The initial desktop study involved the collection of all relevant historical and environmental information. This study highlighted the potential land quality issues associated with the Ebbw Valley's long operational history of iron & steel making, as well as relating to the known activities associated with processing tinplate and galvanised products. This was followed by an intrusive investigation of the potential contaminated areas, in total some 85 bore holes and trial pits were sunk and samples taken and analysed to evaluate ground and groundwater conditions. The site investigation report was circulated and discussed in liaison meetings with the Environment Agency. It was accepted by the Agency that the site conditions did not present a significant risk to the local environment, and there would be no environmental impact from the demolition of the site. |
| Public Relations |
Corus and David Morton produced a bi-monthly Newsletter that was circulated to members of the Local Authority, and within the local community through the Post Office and local Newsagents. The Newsletter informed the community of progress with the demolition of the site and the future planned demolition works. The demolition was also visually demonstrated with the use of photographs. Feedback from the local community was very positive on the content of the Newsletter. This was probably best demonstrated by the co-operation received from the residents of Tyllwyn during the explosive demolition collapse of the Pickle Line. |
| Demolition Statistics |
The demolition process produced some 95,000 tonnes of scrap metal, 11,500 tonnes of waste (of which 10,000 tonnes was inert or non-hazardous), while crushed brick and concrete produced 28,000 tonnes, which was used to fill holes and voids on site. This was mostly achieved by some 20 mechanical machines comprising high reach shears, ground shears, mobile magnet crane, various crabs, scrap baler, brick crusher, loading shovels, lorries, rear dump trucks and a drag line crane, specifically purchased to remove kit and equipment from the basements. |
| Demolition - Civil Works |
To make the site safe and environmentally secure, the civil works involved the sealing of all entrances to basements with pre-cast concrete units for 160 floor openings classed as major holes, while circa 400 depressions being filled with some 28,000 tonnes of site generated rubble. The civil works also included the construction of a basement hydrology system, based on five catchment areas, within the basement system, designed by an independent hydrologist, which utilised the underground basement and tunnels to channel water to the existing site interceptor system. This wou Id then be monitored prior to discharge to the river, in the event of pollution being detected the discharge would be re-directed to the Effluent Plant for treatment before discharge to the River Ebbw Fawr. The system was designed to cope with the worst case storm of 1 in 100 years. |
| Demolition Techniques |
| Modem demolition techniques utilising specialist equipment, such as a high reach shears, have been designed to prevent men working at height, this has significantly reduced the safety risk normally associated with demolition work. High reach shears are used to cut down roof structures to ground level, similarly steel building walls are pre-weakened by hot cutting, walls are then collapsed by either pushing or pulling the wall over. Alternatively buildings can be collapsed by kicking out the structural support with an explosive charge. Steel is then removed by a mechanical grab to be cut up safely at ground level, by hot cutting or cold cutting by shears depending on the size of the steel, thus removing the risk of men working at height. |
| Pickle Line Explosive Demolition – 31 March 2004 |
The most challenging and dramatic demolition sequence undertaken during the three-year demolition programme of the Works was the explosive demolition collapse of No: 4 Pickle Line. |
| Masterplan |
| Corus partnered the Local Authority and the Welsh Development Agency in developing the Masterplan for the former Works site, to establish a step change for the future of Ebbw Vale. Independent consultants were appointed by the Masterplan partners to determine the best future use for the site. The Masterplan had an initial public consultation period in early 2003, with the final plan being released in late 2003. The Masterplan included initial projects for the regeneration of the site, such as the Community Hospital and Learning Campus. The Masterplan is continually being evolved to ensure that it meets its key objective of sustainable regeneration of the Ebbw valley. |
| De-commissioning Managers/Engineers |
D. M. James - Closure Team Manager M. K. Lewis - Project Electrical Engineer M. Atkinson - Project Civil Engineer S. Wilce |